The lines are filling up and in the next few hours the water should arrive in the homes of the whole Sassari area, after several days of dry taps and great inconvenience and protests) of users. The leak of the “Coghinas 2” pipeline near Santa Maria Coghinas was (partially) repaired, on which Enas technicians and workers from external companies have worked continuously for 4 days, in very difficult working conditions.

However, the fault was not completely eliminated. The new joint is still leaking, the leak is defined as "manageable" by the experts. The pipeline in question will therefore need radical intervention (when it will be decided). Now the important thing is that the water reaches the drinking water purifiers and Especially in homes, Abbanoa will have to deal with distribution.