The works are far from completion (there is talk of spring or summer 2025) but there is an important step forward towards the full practicability of the Diana bridge.

The work, on the state road 392 "del Lago del Coghinas", in the municipality of Oschiri, has been partially opened to traffic and from today it is fully usable with the provisions established by Anas. Meanwhile, the works continue, Anas confirmed, "at night to complete the rehabilitation of the vertical structures, starting from 9pm and until 5am". During the night the bridge is closed to traffic. Alternate one-way traffic can be used and «traffic on the bridge is permitted with a load limit of 7.5 tons».

The closure of the Diana bridge dates back to June 2022. The work is a century old, is 315 meters long and is made up of 15 16-metre spans and a 72-metre central arch. The community of Oschiri, but more generally all the people who live in the area between the upper Gallura and the center of Monte Acuto, await the definitive conclusion of the restoration work on the structure.