Anas construction sites on the 195 racetrack in Via San Paolo: long lines of cars lined up at the entrance to Cagliari.
Road widths reduced for drainage layer construction: work continues until March 4thPer restare aggiornato entra nel nostro canale Whatsapp
A long line of cars slowed traffic toward the center of Cagliari this morning. The disruption was caused by the ANAS construction site along the state highway 195 Racc Via San Paolo. The situation tested the nerves of motorists, who were forced to negotiate the nearly two-kilometer queue at a walking pace.
The works, expected to last 15 days, involve the creation of a drainage layer along approximately 3 kilometers of roadway in both directions.
The lane narrowing will affect the section from kilometer 1.800 to kilometer 3.350; subsequently, roadworks will continue between kilometer 0.000 and kilometer 1.150, with the same lane narrowing.
(Unioneonline/vf)