The redevelopment works of the water network in via Oristano in Cagliari have been completed, allowing the reopening of the road. After a few weeks of intervention, the activity was completed and with it the closure to transit and parking: the prohibitions, signs and fences have been removed, with the return of the area. This is the major construction site of Abbanoa, which will continue until June in the Villanova neighborhood .
At the same time, the intervention starts in the upper part of via Iglesias, already closed since yesterday with a (continuous) no-parking sign and the impossibility of driving on the road, blocked at the height of a private garage. In via Oristano the works have seen a small delay linked to the supply of concrete for the restoration . The company in charge, in a work by Abbanoa, will then place the metal plates to allow the transit of vehicles while the concrete finishes drying.